Osino Announces Pre-Feasibility Study Results for Twin Hills Gold Project, Namibia US$783m Pre-Tax NPV, 33% IRR, 2.3 Year Payback

Date/time : 2022-09-06 05:00 AM
Symbol :

OSI

Company : Osino Resources Corp.
Price : 0.57
Market cap : 72,656,137
O/S : 127,466,907
Exchange :

TSXV

Industry :

Gold

Full story

Osino Announces Pre-Feasibility Study Results for Twin Hills Gold Project, Namibia US$783m Pre-Tax NPV, 33% IRR, 2.3 Year Payback

Highlights:

  • NPV of US$783m (pre-tax) and IRR of 33% at 5% discount rate and US$1700/oz gold price.
  • NPV of US$503m (post-tax) and IRR of 26% at 5% discount rate and US$1700/oz gold price.
  • Overall capital cost of US$375 million (incl. US$41m contingency, US$22m capitalised pre-strip, US$20m solar plant and US$8m grid power).
  • Capital estimate includes latest consumer prices and reflects the recent dramatic price escalations especially in steel, reagents, diesel prices and transport costs.
  • Payback period of 2.3 years.
  • 13-year Life-of-Mine (“LOM”) and 5.0 million tonnes per annum (“Mtpa”) processing capacity.
  • Average annual gold production (first 4 years) of 200koz at US$890/oz all-in sustaining cost.
  • Average annual gold production (first 10 years) of 169koz at US$930/oz all-in sustaining cost; LOM average production of 152koz at US$939/oz.
  • LOM gold recovery of 93.2% (first 6 years) and 92.0% (LOM) utilising a conventional 3-stage crushing, ball milling, gravity separation, pre-oxidation and CIL circuit plus a double-lined dry-stack tailings facility.
  • Total Proven and Probable Reserves of 2.150 Moz from 64.3 Mt at 1.04 g/t (at 0.3g/t cut-off).

Osino will host a webinar to discuss the PFS results, today, September 6, 2022 at 11am ET (8am PT). Register here to participate: https://attendee.gotowebinar.com/register/2347595189721541904

VANCOUVER, British Columbia, Sept. 06, 2022 (GLOBE NEWSWIRE) -- Osino Resources Corp. ( TSXV:OSI ) ( FSE:RSR1 ) ( OTCQX:OSIIF ) (" Osino ” or “ the Company ”) is pleased to announce the results of the pre-feasibility study (“ PFS ”) for Osino’s Twin Hills Gold Project (“ Twin Hills “ or the “ Project ”), which is located in central Namibia and is rapidly being advanced through accelerated exploration drilling and fast-tracked development studies.

The PFS was prepared by Lycopodium Minerals Canada (“ Lycopodium ”) in accordance with National Instrument 43-101— Standards of Disclosure for Mineral Projects (" NI 43-101 ") and contemplates a low-risk, technically simple open-pit mine utilizing contract mining and feeding a conventional carbon-in-leach (“ CIL ”) metallurgical plant processing 5 million tonnes of mineralized material per annum.

Heye Daun, Osino’s co-founder, President & CEO commented: “We are very pleased with the results of this PFS which demonstrates that Twin Hills is what we always said it would be, namely a long-life, low-cost and economically robust open pit gold project with significant upside. It is geologically consistent, metallurgically simple and technically low risk with a low capital intensity and significant future upside. We are proud to have been able to deliver this PFS within 3 years of discovery and our vision for the next year is to optimize and improve the project further and to continue to advance Twin Hills to the construction stage. We expect imminent, significant progress on the permitting & project financing side which will assist in continuing to fast-track the project”.

PFS Overview and Financial Analysis

The Twin Hills Gold Project is located within Namibia’s prospective Damara sedimentary mineral belt, in proximity to and along strike of the producing, open-pit Navachab and Otjikoto gold mines.

Twin Hills is a sedimentary-hosted, structurally controlled gold deposit that fits the broad orogenic model and is amenable to conventional open-pit gold mining and carbon-in-leach metallurgical processing.

The table below summarizes the results and key valuation metrics of the PFS on a pre- and post-tax basis.

Table 1: Prefeasibility Study Economic Assessment Summary

US$1700/oz US$1850/oz
Units Pre-Tax Post-Tax Pre-Tax Post-Tax
NPV 5% US$m 783 503 999 638
IRR % 33% 26 % 41% 32 %
Payback Years 2.2 2.3 1.9 2.0
LOM Cashflow US$m 1165 756 1450 934

The financial model was completed on a 100% project basis and includes a 3% gross royalty and 1% export levy to the Namibian government. The economic analysis carried out for the Project uses a cash flow model at a base gold price of US$1,700/oz and a 5% discount rate.

A sensitivity analysis utilising a range of gold prices and operating variables was completed. The results are tabulated in table 4 on page 5.

The financial assessment of the Project was carried out on a 100% equity basis, not accounting for potential sources of funding which may include debt. Osino’s understanding of current Namibian tax regulations were applied to assess the tax liabilities.

The key operating assumptions and economic parameters used in the PFS are as follows:

Table 2: Key Operating Assumptions

Item Units Amount
Life of Mine Years 13
Gold price (base case) US$/oz 1 700
Mining dilution % 5,0%
Ore loss % 3,5%
Gold Recovery % 92,0%
Royalty (tax-deductible) % 3,0%
Export Levy % 1,0%
Life-of-Mine Production Parameters
Ore Tonnes Mined Kt 64 287
Ore Grade Mined g/t 1,04
Ore Metal Mined (Proven & Probable Reserves) Koz 2 150
Waste Tonnes Mined Kt 285 013
Strip Ratio 4,43
LOM Gold Production Koz 1 978
LOM Average Annual Gold Production (years 1 – 10) koz annum 169
Average Annual Gold Production (years 1 – 4) koz annum 200
Life-of-Mine Unit Costs per Tonne Mined/Processed
Refining cost US$/oz 0.55
Gold transport cost US$/oz 2.20
Mining Cost (per tonne mined) US$/t 2,62
Variable Processing Cost (per tonne processed) US$/t 8.97
Fixed Processing Cost (G&A) US$m/annum 18,31
Overall Processing unit Cost (per tonne processed) US$/t 12,45
Unit Costs per Ounce Produced
LOM Average Operating Costs 1 US$/oz 831
LOM Average Cash Costs 2 US$/oz 931
LOM Average All-in Sustaining Costs 3 US$/oz 939
Capital Costs
Construction Capital (Lycopodium Estimate) US$m 283
Contingency (14,4%) US$m 41
Capitalised Pre-strip US$m 22
PV Plant US$m 20
Grid power extra (additional to signed PSA) US$m 8
First Fills (mostly steel balls) US$m 2
Total Project Capital (incl. contingency) US$m 375
Sustaining Capital US$m 74

Notes:
1. Mining, processing plus on-site G&A
2. Operating costs plus selling costs, royalties & levies
3. Cash costs plus sustaining capital (incl. closure costs & salvage value)

A summary of the production schedule in tabulated format and cash flow model with key economic results can be viewed in Figure 16 below.

It should be noted that there is scope for significant optimization and improvement to the mine design and production schedules which will be reflected in the next technical assessment of the project.

Sensitivity Analysis

An after-tax sensitivity analysis to the key project variables was carried out which indicates that the project is most sensitive to a change in grade or gold recovery, as indicated by the slope of the blue line in the diagram below.

At a stressed economic scenario of a gold price of US$1400/oz and an elevated discount rate of 10% the project still reflects a post-tax NPV of US$114m.

The project is most sensitive to changes in gold grade, with every 5% change in gold grade resulting in a change in NPV of around 15%. This is indicated by the slope of the blue line graph in the diagram below, which confirms that the project NPV is most sensitive to changes in the average gold grade.

Figure 1: Post-Tax Project NPV Sensitivity to Variations in Key Project Parameters at US$1700/oz
https://www.globenewswire.com/NewsRoom/AttachmentNg/6862aff1-0511-4aca-a5f5-d8a3a327ed71

Table 3: Two-factor Post-Tax Project NPV Sensitivity Analysis

Discount Rate & Gold Price - Post-Tax NPV 5% Sensitivity
1400 1500 1600 1700 1800 1900 2000
5 % 228 320 412 503 593 683 773
6 % 202 290 378 464 550 636 721
7 % 177 262 345 428 510 591 673
8 % 154 235 316 395 473 550 628
9 % 133 211 288 364 438 513 587
10 % 114 189 263 335 406 477 548
Mill Feed Grade & Gold Price - Post-Tax NPV 5% Sensitivity
1400 1500 1600 1700 1800 1900 2000
0,94 94 182 266 348 431 512 594
0,99 162 252 339 426 512 598 684
1,04 228 320 412 503 593 683 773
1,09 293 389 485 580 674 769 863
1,14 357 458 557 656 755 854 953
Mining Unit Cost & Gold Price - Post-Tax NPV 5% Sensitivity
1400 1500 1600 1700 1800 1900 2000
2,36 273 365 457 547 637 727 817
2,49 251 343 435 525 615 705 795
2,62 228 320 412 503 593 683 773
2,75 205 298 390 481 571 661 751
2,88 182 276 367 459 549 640 730
Processing Cost (Variable) & Gold Price - Post-Tax NPV 5% Sensitivity
1400 1500 1600 1700 1800 1900 2000
7,90 255 347 439 529 619 709 799
8,34 241 334 425 516 606 696 786
8,78 228 320 412 503 593 683 773
9,22 215 307 399 490 580 670 760
9,66 201 294 386 477 567 658 748
Construction Capex & Gold Price - Post-Tax NPV 5% Sensitivity
1400 1500 1600